First of two rapid exit taxiways from runway 34 enters operation
The first of two rapid exit taxiways from runway 34 at Zurich Airport entered operation during the night of 25 to 26 November. Rapid exit taxiways allow aircraft to vacate the runway more quickly after landing, enabling the spacing between arriving aircraft to be optimised. This helps reduce delays and improves the stability of flight operations.
Construction of the two new rapid exit taxiways from runway 34 began in April 2024. To minimise disruption to regular flight operations, most of the work was carried out at night after the airport had closed for the day. Following the commissioning of the southern rapid exit taxiway, the northern rapid exit taxiway is expected to enter operation in November 2027.
Long-term infrastructure project
Planning for the rapid exit taxiways from runway 34 dates back to 2003. At that time, Zurich Airport Ltd. submitted its first planning approval application as part of the provisional operating regulations. Following several legal proceedings and based on the Sectoral Aviation Infrastructure Plan (SAIP), planning approval for the rapid exit taxiways from runway 34 became legally binding in 2019. The implementation of the project was initially delayed due to the coronavirus pandemic. Construction then began in 2024.
Part of the long-term development of the runway system
The rapid exit taxiways will not result in any changes to approach procedures. They will allow aircraft landing from the south on runway 34 to vacate the runway more quickly, reducing the risk of delays. Rapid exit taxiways are already in operation on the other landing runways at Zurich Airport. The rapid exit taxiways are part of the measures outlined in the Sectoral Aviation Infrastructure Plan (SAIP) for the further development of Zurich Airport's runway and taxiway system. Together with other infrastructural and operational measures, they are intended to further improve the safety and stability of flight operations.